• Project Name
  • Location
  • Name of Client(s)
  • 92 IRM Project BruneiBrunei Shell Petroleum (BSP)

    • Year: 2010 – 2015
    • Vessel Name, Vessel Type, & Method(s):DSV Ajang Harapan/ IES Pioneer – Air Diving & K ROV 03-Cougar XT
    • Start Date (MM/YY): Mar-10
    • Completion Date (MM/YY): Mar-15
    • Scope of Work:
      Long term Provision of Underwater Inspection, Repair & Maintenance Services for 5 years period from DP vessel using Air, Sat Diving & ROV.
      Provision of all kinds of subsea IRM activities including baseline platform inspection, I/J- Tube installation, Anode installation, Pipeline Repair using PLIDCO Clamps, Risers Repair, Free Spans Corrections & similar IRM activities.
  • 91 JDA Gas Balancing Evacuation (EVA) Project MalaysiaClient: TLO
    End Client: Trans Thai Malaysia

    • Year: 2014
    • Vessel Name, Vessel Type, & Method(s):Kreuz Installer sat and Air Diving + K ROV 02
    • Start Date (MM/YY): May-14
    • Completion Date (MM/YY): Oct-14
    • Scope of Work:
      1. Install 24” x 75m long Spool at MRP platform
      2. Flooding of 24” x 75Km Gas Export Pipeline
      3. Metrology, spool fabrication and installation 24” closing spool at MRP.
      4. Carryout Pre-commissioning of 24” x 75Km Gas Export pipeline(Pigging, Cleaning, Gauging and Hydrotesting)
      5. Run Intelligent Pig through 24” x 75Km Gas Export Pipeline from MRP to PLTS end.
      6. Cut the DMA Initiation wire from 24” Gas Export Pipeline at MRP end and recover the 750m long wire to DSV deck.
      7. Anode CP Survey at Platform MRP (By ROV)
      8. EMP (Environmental Monitoring Performance) Survey by ROV
      9. Scour survey at MRP jacket legs
      10. ROV Survey of 24″” Gas Export Pipeline (At crossing locations)
  • 90 Su Tu Nau Field Development Block 1501 Offshore Vietnam VietnamPTSC Mechanical and Construction / SOC

    • Year: 2014
    • Vessel Name, Vessel Type, & Method(s):Swiber Conquest (Barge)
      Air and Sat Diving
    • Start Date (MM/YY): May-14
    • Completion Date (MM/YY): Oct-14
    • Scope of Work:
      1. Stinger Checks for pipelay – 6”, 10”, 12”, 14” & 18” = Air Diving Scope
      2. Spool Metrology + Fabrication & installation = 22nos
      3. Expansion Loops – 03 nos
      4. Flooding of Pipelines – 06 no
      5. Riser Guard Installation 27MT – 01 no
      6. SSIV installation 63MT – 01 no
      7. Riser Clamps installation 18” – 03 nos
      8. 18” Riser Installation – 01 no
  • 89 South Belut Project IndonesiaConocoPhilips/ RSC

    • Year: 2014
    • Vessel Name, Vessel Type, & Method(s):Barge Triumphant
      Air Diving
    • Start Date (MM/YY): Sep-14
    • Completion Date (MM/YY): Sep-14
    • Scope of Work:
      45 Ton Riser Guard (1no) Installation
  • 88 Cendor Field Development Phase 2 Project MalaysiaTL Offshore

    • Year: 2014
    • Vessel Name, Vessel Type, & Method(s):Kreuz Installer (DP DSV) Air and Sat Diving, ROV
    • Start Date (MM/YY): Aug-14
    • Completion Date (MM/YY): Sep-14
    • Scope of Work:
      1. Bridge Bumper Recovery and handover to SK900
      2. Riser Clamps Installation
      • 6 x 12” Riser Clamp Installation at Platform CDWB
      • 6 x 12” Riser Clamp Installation at Platform CDWC
      3. Existing Riser Clamp Removal
      4. WD PLET Pre-Flushing and FSO Flowline Removal
      5. WD PLET Chute Installation and Temporary Valve Support Removal
      6. Tie-in and Leak Test of 8” Flexible Riser
      7. FSO Flowline Re-routing and deoiling operation from 8″” Flexible Risers
      8. Lower down the 8” FSO Flowline from FSO and removal of Buoyancy Modules (4 nos)
      9. 6” x 800m Old Manuli Hose Recovery and Cutting Operation
      10. 6” x 1km New Manuli Hose Recovery and Cutting Operation + 2 nos Buoyancy Modules
  • 87 Provision of ROV (QUASAR) ThailandMermaid Offshore Services
    End Clients: PCML

    • Year: 2014
    • Vessel Name, Vessel Type, & Method(s): Lewek Atria
    • Start Date (MM/YY): Aug-14
    • Completion Date (MM/YY): Sep-14
    • Scope of Work:
      Yetagun North 10” Pipeline Free-span Correction
  • 86 Provision of ROV (QUASAR) ThailandMermaid Offshore Services
    End Clients: PTT

    • Year: 2014
    • Vessel Name, Vessel Type, & Method(s): Lewek Atria
    • Start Date (MM/YY): Aug-14
    • Completion Date (MM/YY): Aug-14
    • Scope of Work:
      Full platform inspection at Erawan Field PRP Platform
  • 85 Provision of ROV (QUASAR) ThailandMermaid Offshore Services
    End Clients: Chevron

    • Year: 2014
    • Vessel Name, Vessel Type, & Method(s): Lewek Atria
    • Start Date (MM/YY): Jun-14
    • Completion Date (MM/YY): Jul-14
    • Scope of Work:
      ACFM, Node Cleaning, GVI, Hull Survey & mooring chain inspection with CP probe
  • 84 Manora Field Development Project ThailandEquatoriale Services Pte Ltd

    • Year: 2014
    • Vessel Name, Vessel Type, & Method(s): 1MAS 300 (Barge) Air and Sat Diving
    • Start Date (MM/YY): May-14
    • Completion Date (MM/YY): Jun/Jul-14
    • 1. Laying mooring chain & tension
      2. Hook up chain to SBM
      3. Laying 2 x 8″” dia x 100m Flexible
      4. Tie-in Flexible to PLEM (Rigid Spool)
      5. Tie-in Flexible to SBM
      6. Flexible Leak Test
      7. Floating Hoses installation
      8. Floating Hoses leak test
  • 83 Pipeline Replacement Project BruneiSOC / BSP

    • Year: 2014
    • Vessel Name, Vessel Type, & Method(s):Swiber Victorious (Barge) Air Diving
    • Start Date (MM/YY): May-14
    • Completion Date (MM/YY): May-14
  • 82 Cendor Field Development Phase Project MalaysiaTLO/Petrofac

    • Year: 2014
    • Vessel Name, Vessel Type, & Method(s):Kreuz Installer (DP DSV) Air and Sat Diving
    • Start Date (MM/YY): Mar-14
    • Completion Date (MM/YY): Jul-14
    • Scope of Work:
      Transportation & Installation of Offshore Structures & Pipelines
      1. Laying 2 X 8” dia Flexible Riser from FPSO to PLET -B(through the MWA)
      2. Laying 2 X 8” dia Flexible Riser from FPSO to PLET -C(through the MWA)
      3. Laying 2 X 8” Flexible flowline from Existing PLET-B to CDW-B
      4. Laying 2 X 8” Flexible flowline from Existing PLET-C to CDW-C
      5. Laying 2 X 12” Flexible flowline from Existing FPSO to CDW-B
      6. Laying 2 X 12” Flexible flowline from Existing FPSO to CDW-C
      7. Tie-in @ FPSO, CDW-B, CDW-C, PLET-B and PLET-C
      8. FPSO mooring chains installation
      9. Configure MWA clamps
      10. Floating Hoses instalation
  • 81 PRP 3 Heera RD Phase II Project – Additional Pipeline Project IndiaLWIN

    • Year: 2014
    • Vessel Name, Vessel Type, & Method(s): Kreuz Glorious (Barge)
    • Start Date (MM/YY): Jan-14
    • Completion Date (MM/YY): May/Jun-14
    • Scope of Work:
      Riser Stalk Installation
      1. 6” Stalk On riser : 30 nos
      2. 12” Stalk on Riser : 14 nos
      3. 16” Stalk on Riser : 5 nos
      4. 4” Stalk on Riser : 24 nos
    • Year: 2013
    • Vessel Name, Vessel Type, & Method(s): Kreuz Supporter (Constructions Barge) Sat/ Air Diving
    • Start Date (MM/YY): Nov-13
    • Completion Date (MM/YY): May/Jun-14
  • 80 TOTAL Yadana Project MyanmarSOC / TOTAL

    • Year: 2013 – 2014
    • Vessel Name, Vessel Type, & Method(s): Kaizen 4000 (Barge) Air Diving
    • Start Date (MM/YY): Dec-13
    • Completion Date (MM/YY): Apr-14
    • Scope of Work:
      • Air diving support for Jacket Installation
  • 79 Yetagun Project MyanmarHHI

    • Year: 2014
    • Vessel Name, Vessel Type, & Method(s): HD 2500 (Barge)
    • Start Date (MM/YY): Jan-14
    • Completion Date (MM/YY): Mar-14
    • Scope of Work:
      • 2 10″ Riser Installation
      • 1 10″ Pipeline installation
  • 78Saturation Diving System Support for Total Project Indonesia TOTAL

    • Year: 2014
    • Vessel Name, Vessel Type, & Method(s): ASL Offshore 1 (Barge)
    • Start Date (MM/YY): Feb-14
    • Completion Date (MM/YY): Apr-14
    • Scope of Work:
      • Debris Clearance and preparations works for jacket installation
  • 77 South Belut Project IndonesiaCOPI /RSC

    • Year: 2013 – 2014
    • Vessel Name, Vessel Type, & Method(s): Seamec Princess (DP DSV)
    • Start Date (MM/YY): Feb-14
    • Completion Date (MM/YY): Apr-14
    • Scope of Work:
      • Topside J-tube Preparations at NBCPP
      • Pre lay mattress installation at crossings
      • UTA mud mat installation
      • Umbilical Pull-in through J-tube
      • J-tube Seal assembly installation and activation
      • Installation of 9.70 km Umbilical (with carousel) from NBCPP to SDU-01 (TYPE-1)
      • Type-1 Umbilical testing from NBCPP
      • Installation of FFS ( Fishnet Friendly Structure)
  • 76 ABKATUN-D Project MexicoPEMEX / SOC

    • Year: 2013 – 2014
    • Vessel Name, Vessel Type, & Method(s): Swiber Concorde / Aziz (Barge) Air Diving
    • Start Date (MM/YY): Feb-14
    • Completion Date (MM/YY): Apr-14
    • Scope of Work:
      • Installation of subsea componenet & provision of Diving Personnel and Equipment for:
      • Installation Pipeline
      • Mattress and other subsea facilities
  • 75 BWK Project IndonesiaCOOEC/SOC

    • Year: 2013
    • Vessel Name, Vessel Type, & Method(s): PJW 3000 (Barge) Air Diving
    • Start Date (MM/YY): Feb-14
    • Completion Date (MM/YY): Apr-14
    • Scope of Work:
      • BWK Project
  • 74 South Belut Project IndonesiaCOPI /RSC

    • Year: 2013 – 2014
    • Vessel Name, Vessel Type, & Method(s): Kreuz Installer (DP DSV)
    • Start Date (MM/YY): Feb-14
    • Completion Date (MM/YY): Apr-14
    • Scope of Work:
      • Phase II Umbilical Lay
      • including E/H flying leads
      • Mattresses
      • UTA’s and FFS Installation
      • Closings Spools
      • Venturi Flying Leads
      • Venturi Flow-meters
      • Grouting and Mattresses
      • Installation
      • 14” Pipeline & 8” Flowline De-watering and nitrogen Packing
      • Pre-commissioning activities ( Valve Operation at Inline Tee and PLEM)
  • 73 Zawtika Project Myanm aSOC / PTTEPI

    • Year: 2013 – 2014
    • Vessel Name, Vessel Type, & Method(s): PJW 3000 (Barge) Air Diving
    • Start Date (MM/YY): Feb-14
    • Completion Date (MM/YY): Apr-14
    • Scope of Work:
      • Abandon Pipeline Recovery and Concrete Mattress Installation
  • 72Santos Indonesian ProjectIndonesiaSantos / RSC

    • Year: 2013 – 2014
    • Vessel Name, Vessel Type, & Method(s): Resolute (Barge)
    • Start Date (MM/YY): Dec-13
    • Completion Date (MM/YY): Jan-14
    • Scope of Work:
      • Riser Installation
  • 71Transportation & Installation of offshore Structures and PipelinesBruneiSOC/BSP

    • Year: 2013
    • Vessel Name, Vessel Type, & Method(s): Conquest (Barge) ( Air Diving)
    • Start Date (MM/YY): Aug-13
    • Completion Date (MM/YY): Dec-13
    • Scope of Work:
      • Air diving Suppport for Pipe lay activities
      • Riser Stalk on installation
      • J tube Installation
      • Spool Tie-in
      • Mid Water Flange tie-in
  • 70South Belut ProjectIndonesiaSOC/ COPI

    • Year: 2013 – 2014
    • Vessel Name, Vessel Type, & Method(s): Kreuz Glorious
    • Start Date (MM/YY): May-13
    • Completion Date (MM/YY): Jan-14
    • Scope of Work:
      • Accomodation Support
  • 692010 -2012 Transportation and Installation of EMEPMI Offshore FacilitiesMalaysiaTLO / ExxonMobil

    • Year: 2013
    • Vessel Name, Vessel Type, & Method(s): Kreuz Installer (DP DSV)
    • Start Date (MM/YY): Feb-13
    • Completion Date (MM/YY): Nov-13
    • Scope of Work:
      • Flooding of Pipelines at various Platform of Tapis Field
      • Riser Installation: Metrology, Fabrication and Installation of 10″, 12″, 14″, 16″ & 18″ Risers/Riser Clamps at Tapis and
      Damar Fields
      • Closing Spools: Metrology, Fabrication and Installation of 6″, 10″, 12″, 14″, 16″ & 18″ Closing Spools at Tapis and
      Damar Fields
      • Riser Guard: Installation of Riser Guards at various Platform of Tapis Field
      • Dummy Spool: Removal of Dummy Spools at TaF/GuE Tie In location – Tapis Field
      • Boat Fenders: Removal of Boat Fender at TaD Platform – Tapis Field
      • J-Tube Installation: Metrology, Fabrication and Installation of J-Tube Installation at TaA Platform – Tapis Field
  • 68South Belut ProjectIndonesiaCOPI / RSC

    • Year: 2013
    • Vessel Name, Vessel Type, & Method(s): Kreuz Supporter
      (Constructions Barge)
      Sat/ Air Diving
    • Start Date (MM/YY): Aug-13
    • Completion Date (MM/YY): Nov-13
    • Scope of Work:
      • Recovery of Laydown Wire and Flooding of 14″ x 9.4Km & 7.4Km Pipeline
      • Removing the Dummy spool
      • 09 X 14” Inline Tee installation
      • Subsea XT to 14” Pipeline Tie-in Including Venturi Flow meter and Check Valve
      • J-Tube and riser clamp installation
      • South Belut Venturi Flow-meter Protection Frame Installation
      • Dewatering & Nitrogen Purging
  • 67Sisi Nubi Phase 2B and Peciko Phase 7B Development ProjectIndonesiaSOC/TOTAL

    • Year: 2013
    • Vessel Name, Vessel Type, & Method(s): Swiber PJW 3000 (Barge) Air and Sat Diving
    • Start Date (MM/YY): Aug-13
    • Completion Date (MM/YY): Nov-13
    • Scope of Work:
      • Air Diving Support for Barge Activities as required
  • 66Su Tu Nau ProjectVienamHHI

    • Year: 2013
    • Vessel Name, Vessel Type, & Method(s): HD 2500 (Barge) Air and Sat Diving
    • Start Date (MM/YY): May-13
    • Completion Date (MM/YY): Nov-13
    • Scope of Work:
      • Subsea Template Installation ( Cut-off of Lifting Trunion and removal of docking pile guide)
      • 2 Nos Jacket and Boat Landing Installation Removal of Bouyancy Tanks
  • 65Naga And Pelikan ProjectIndonesiaSOC / Permier Oil

    • Year: 2013
    • Vessel Name, Vessel Type, & Method(s): Crest Odyssey (DP DSV) Sat Diving
    • Start Date (MM/YY): Oct-13
    • Completion Date (MM/YY): Nov-13
    • Scope of Work:
      • 10 Nos Spool Installation
      • SSIV Installation
      • Closing Spool Metrology
      • Final Closing Spool Installations
      • N & P Pipeline Start up wire removal
      • 14” Naga Pipeline Flooding
      • 12” Pelikan Pipeline Flooding
      • Concrete Mattress Installation
      • Closing Spool Installation at Naga Platform
      • Installation of Bar T Protection Frame
      • Closing Spool Installation at Pelikan Platform
      • Carry out As Built Surveys at all locations
  • 64Ruby Field Development ProjectIndonesiaSOC / Permier Oil

    • Year: 2013
    • Vessel Name, Vessel Type, & Method(s): 1 Mas 300 (Barge) Sat & Air Diving
    • Start Date (MM/YY): Jul-13
    • Completion Date (MM/YY): Aug-13
    • Scope of Work:
      • 14″ Spool tie-in
      • SSIV and umbilical installation
  • 63SHWE Field Development ProjectMyanmarHHI

    • Year: 2013
    • Vessel Name, Vessel Type, & Method(s): Seamec Princess (DP DSV) Sat Diving
    • Start Date (MM/YY): Jun-13
    • Completion Date (MM/YY): Jul-13
    • Scope of Work:
      • SHWE Field Development Project
  • 62WMO PHE Pipeline ProjectIndonesiaSOC / PHE WHO

    • Year: 2013
    • Vessel Name, Vessel Type, & Method(s): 1 Mas 300 (Barge) Sat & Air Diving
    • Start Date (MM/YY): Jun-13
    • Completion Date (MM/YY): Jul-13
    • Scope of Work:
      • KE 54 Leak Repair
  • 61Naga And Pelikan ProjectIndonesiaSOC/ Permier Oil

    • Year: 2013
    • Vessel Name, Vessel Type, & Method(s): Conquest (Barge) Air Diving
    • Start Date (MM/YY): May-13
    • Completion Date (MM/YY): Jun-13
    • Scope of Work:
      • Stinger Checks and other air diving support as required
  • 60Champion Waterflood Project (EPCI)BruneiSOC /BSP

    • Year: 2013
    • Vessel Name, Vessel Type, & Method(s): Crest Odyssey (DP DSV) ROV
    • Start Date (MM/YY): May-13
    • Completion Date (MM/YY): Jun-13
    • Scope of Work:
      • Subsea Installation of following facilities:• 500 Concrete Mattress Operations
    • Year: 2013
    • Vessel Name, Vessel Type, & Method(s): Jascon 25 (DP3 DSV) Air Diving and ROV
    • Start Date (MM/YY): May-13
    • Completion Date (MM/YY): Aug-13
    • Scope of Work:
      • Subsea Installation of following facilities:• 11 Nos Flexible Pipeline includes 16″, 12″ and 8″ Dia flexibles• 8 Nos Type 1 and Type 2 Umbilical installation• 4 Nos composite Power cable installation• Pre and Post lay survey
    • Year: 2013
    • Vessel Name, Vessel Type, & Method(s): Resolute (Barge)
    • Start Date (MM/YY): Oct-13
    • Completion Date (MM/YY): Dec-13
    • Scope of Work:
      • Subsea Riser installation with clamps• 5 Nos J tube installation with clamps• Flexible flow line tie-in to risers• Subsea cable pull-in inside J-tube• Grout bag Support

      • Post Laying Concrete Mattress Operations

      • Drop object protection frame installation

    • Year: 2013
    • Vessel Name, Vessel Type, & Method(s): Ajang Harapan (DP DSV) Air Diving and ROV
    • Start Date (MM/YY): Nov-13
    • Completion Date (MM/YY): Nov-13
    • Scope of Work:
      • Cable laying and pull-in• Pre and Post lay survey
  • 59BSP Major Project C090220/MPM (Transportation & Installation)Brunei SOC / BSP

    • Year: 2013
    • Vessel Name, Vessel Type, & Method(s): JSwiber Resolute (Barge) Air Diving
    • Start Date (MM/YY): Apr-13
    • Completion Date (MM/YY): Sep-13
    • Scope of Work:
      • Riser and Riser Clamp Installation
      • Metrology and Closing of Riser Clamps Installation of hold-back wires and connection of Start-up wires
  • 58Transportation & Installation of Offshore Structures and PipelinesBrunei SOC/BSP

    • Year: 2013
    • Vessel Name, Vessel Type, & Method(s): Jaya Installer (Barge) Sat & Air Diving
    • Start Date (MM/YY): Apr-13
    • Completion Date (MM/YY): Oct-13
    • Scope of Work:
      • Installation of Subsea Riser Clamps
      • Removal of Knee Brace
      • Installation of Subsea Riser Clamps
      • Installation of Subsea J Tube Clamps
      • Adjustment of PID to Riser orientation
      • Installation of PID metrology to Riser and close riser clamps
      • Installation of Cable Supporting Sandbags
      • J Tube Sealing
      • Installation of Metrology and Subsea Spool Tie In
  • 57Zawatika Pipeline Project Phase 1 A (140 m)MyanmarSOC / PTTEP

    • Year: 2013
    • Vessel Name, Vessel Type, & Method(s): Mermaid Commander (DP DSV) Seamec Princess (DP DSV)
    • Start Date (MM/YY): Apr-13
    • Completion Date (MM/YY): Oct-13
    • Scope of Work:
      • Hyperbaric Welding and Installation of 28″ Dia Tie-in spools between Riser and Pipeline at 138 m water depth
      • Flange Protector installation
      • Removal of the Riser Support
      • Installation of 28” Spool Bend Protection
  • 56SHWE Field Development ProjectMyanmarHD289 (Barge) Saturation Diving

    • Year: 2013
    • Vessel Name, Vessel Type, & Method(s): HD289 (Barge) Saturation Diving
    • Start Date (MM/YY): Feb-13
    • Completion Date (MM/YY): May-13
    • Scope of Work:
      • Umbilical Installation
      • MND-D HFL & ASD Installation
      • 14” Pipeline Free Span Correction
      • 32” Riser Spool Installation
      • Umbilical Testing
  • 55TOTAL Yadana Project MyanmarSOC/TOTAL / TEPM

    • Year: 2013
    • Vessel Name, Vessel Type, & Method(s): Swiber PJW 3000 (Barge) Air Diving
    • Start Date (MM/YY): Feb-13
    • Completion Date (MM/YY): Apr-13
    • Scope of Work:
      • Contingency Air Diving
  • 54TOTAL Yadana Project MyanmarSOC/TOTAL / TEPM

    • Year: 2013
    • Vessel Name, Vessel Type, & Method(s): HD289 (Barge) Saturation Diving
    • Start Date (MM/YY): Feb-13
    • Completion Date (MM/YY): May-13
    • Scope of Work:
      • Umbilical Installation
      • MND-D HFL & ASD Installation
      • 14” Pipeline Free Span Correction
      • 32” Riser Spool Installation
      • Umbilical Testing
  • 53Zawtika Pipeline Project MyanmarSOC / PTTEP

    • Year: 2013
    • Vessel Name, Vessel Type, & Method(s): Swiber Conquest (Barge) Air Diving
    • Start Date (MM/YY): Jan-13
    • Completion Date (MM/YY): Mar-13
    • Scope of Work:
      • Stinger Checks and other air diving support as required
  • 52B193 Process Platform Project (WD 65 – 80m)India SOC / ONGC

    • Year: 2012 – 2013
    • Vessel Name, Vessel Type, & Method(s): Kreuz Supporter
      (Constructions Barge)
      Sat/ Air Diving
    • Start Date (MM/YY): Oct-12
    • Completion Date (MM/YY): May-13
    • Scope of Work:
      • Subsea Installation of following facilities:
      • B-193 Pipe Line works
      • Umbilical laying + pull-in through J-Tube
      • Cable Lay + pull-in through J-Tube from B-193LP to B-193AF-HP
      • Spool Tie-ins
      • B-193 Process Platform Scope
      • Lift and Repair 20 Inch Pipe Line
      • Installation of 2 Nos 20″ dia spool and 2 Nos 4″ Dia spool
      • 8” B-22 – B-193AP Flexible pull-in on north face of Platform B-193-AP
  • 51Cluster 7 Pipeline Project (WD 60 – 80 m)India SOC / ONGC

    • Year: 2012 – 2013
    • Vessel Name, Vessel Type, & Method(s): Kreuz Supporter
      (Constructions Barge)
      Sat/ Air Diving
    • Start Date (MM/YY): Oct-12
    • Completion Date (MM/YY): May-13
    • Scope of Work:
      • Subsea Installation of following facilities:
      • B-193 Pipe Line works
      • Umbilical laying + pull-in through J-Tube
      • Cable Lay + pull-in through J-Tube from B-193LP to B-193AF-HP
      • Spool Tie-ins
      • B-193 Process Platform Scope
      • Lift and Repair 20 Inch Pipe Line
      • Installation of 2 Nos 20″ dia spool and 2 Nos 4″ Dia spool
      • 8” B-22 – B-193AP Flexible pull-in on north face of Platform B-193-AP
  • 50WMO PHE Pipeline ProjectIndonesiaSOC / PTTEP / MOGE

    • Year: 2012 – 2013
    • Vessel Name, Vessel Type, & Method(s): Resolute (Barge) Air and Saturation Diving
    • Start Date (MM/YY): Aug-12
    • Completion Date (MM/YY): Jan-13
    • Scope of Work:
      • Installation of subsea component & provision of Diving Personnel and Equipment for:
      • PLEM Installations
      • Riser & Clamp Installations
      • Tie-in spool installations
      • Other Subsea Installations
  • 49TLO-West Desaru ProjectMalaysiaTL Offshore / Petrofac

    • Year: 2012 – 2013
    • Vessel Name, Vessel Type, & Method(s): Kreuz Installer (DP DSV) Saturation Diving
    • Start Date (MM/YY): Dec-12
    • Completion Date (MM/YY): Feb-13
    • Scope of Work:
      • Laying of 8” flexible from PLET to FSO
      • Laying of 6” Manuli hose
      • Removal and recovery of old manuli hose and buoyancy module installed along hose
      • Metrology, fabrication and tie-in of 8” subsea spools
      • Installation of WD PLET
      • Installation of concrete mattress along the flexible
  • 48Swiber Mexico ProjectMexicoSOC / PEMEX

    • Year: 2012
    • Vessel Name, Vessel Type, & Method(s): Swiber Aziz (Barge) Air Diving
    • Start Date (MM/YY): Nov-12
    • Completion Date (MM/YY): Nov-12
    • Scope of Work:
      • Stinger Checks and other air diving support as required
  • 47Zawatika Pipeline Project Phase 1A (130 – 140 m)MyanmarSOC / PTTEP / MOGE

    • Year: 2012 – 2013
    • Vessel Name, Vessel Type, & Method(s): Swiber PJW 3000 (Barge) Air Diving
    • Start Date (MM/YY): Sep-12
    • Completion Date (MM/YY): Feb-13
    • Scope of Work:
      • Installation of subsea components & provision of Diving Personnel and Equipment for: – 28″ dia Pipeline installation
  • 46SHWE Field Development Project (WD 140 m)IndonesiaHyundai Heavy Industries

    • Year: 2012
    • Vessel Name, Vessel Type, & Method(s): HD 2500 (Barge) Sat & Air Diving
    • Start Date (MM/YY): Sep-12
    • Completion Date (MM/YY): Sep-12
    • Scope of Work:
      • Installation of subsea components & provision of Diving Personnel and Equipment for:
      • Umbilical Installation
      • MND-D HFL & ASD Installation
      • 14” Pipeline Free Span Correction
      • 32” Riser Spool Installation
      • Weld Head Interface Umbilical Test
  • 45Pearl Oil Pipeline ProjectIndonesiaSOC / Pearl Energy

    • Year: 2012
    • Vessel Name, Vessel Type, & Method(s): Swiber Conquest (Barge) Air Diving
    • Start Date (MM/YY): Sep-12
    • Completion Date (MM/YY): Sep-12
    • Scope of Work:
      • Stinger Checks and other air diving support as required
  • 44BAWAL Sub-sea Development ProjectIndonesiaConocoPhillips

    • Year: 2012
    • Vessel Name, Vessel Type, & Method(s): Kreuz Supporter (Constructions Barge) Sat/ Air Diving
    • Start Date (MM/YY): Sep-12
    • Completion Date (MM/YY): Sep-12
    • Scope of Work:
      • 8″ Spool Installation between Bawal well-01 and Bawal-01 Tee (on the 14″ Pipeline)
      • 8″ Spool to be installed in 3 sections including one metrology section
      • Check valve and Venturiflowmeter to be assembled with spool section on deck using kamos gaskets and PTFE
      • Coated bolts and nuts
      • Installation of one flange Protection frame which will cover one flange connection and one Tee connection on the
      spool
      • Installation of Check Valve and venturiflowmeter Protection Frame
      • Installation of 1 off Hydarulic Flying Lead (HFL’s) from UTA to Bawal well 01
      • Installation of 2 off Electrical Flying Leads (EFL’s) from UTA to Bawal well 01
      • Connecting 3 off Electrical Flying leads from EDM to UTH-3 (within the UTA)
      • Installation 1 off x 15m Electrical Flying Lead from Bawal well-01 to the Venturiflowmeter on the 8″ Spool
      • Installation of 3 off Electrical and 1 off Hydraulic Flying Leads from UTH-1 to UTH-2 (within SDU-01)
      • Installation of 6m x 2m Geotextile coated concrete mattresses on the EHFL’s from UTA to Bawal Well -01
      • Installation of 1 nos.ea of pumped grout bags underneath the check valve and venturiflowmeter
      • Fabrication and Hydrotesting of the 8″ closing spool on deck
  • 43TOTAL E&P Brunei ProjectBruneiTOTAL E&P / SOC

    • Year: 2012
    • Vessel Name, Vessel Type, & Method(s): Kreuz Glorious
    • Start Date (MM/YY): Aug-12
    • Completion Date (MM/YY): Dec-12
    • Scope of Work:
      • Accomodation Support
  • 42TLO Murphy Sarawak ProjectBintulu Field MalaysiaTL Offshore / Murphy Oi

    • Year: 2012
    • Vessel Name, Vessel Type, & Method(s): Kreuz Installer (DP DSV) Sat & Air Diving
    • Start Date (MM/YY): Aug-12
    • Completion Date (MM/YY): Oct-12
    • Scope of Work:
      • Riser Clamp Installation for 8″ Riser
      • 8″ Riser Installation
      • Riser Guard Installation
      • Pre-Comm activities for 8″ WP-PA to PT-SA Pipeline-13.2km
      • 8″ Spool Installation at PT-SA & WP-PA Platform
      • Installation of 20″ WYE with Protection Structure
      • Spool Tie-in for 8″ and 20″ Pipeline at WYE1 & WYE2 and SN-PA Location
  • 41SOGT ProjectMalaysiaALAM Maritim Sdn Bhd / Petronas

    • Year: 2012
    • Vessel Name, Vessel Type, & Method(s): Magnificent (Barge) Sat & Air Diving
    • Start Date (MM/YY): Jul-12
    • Completion Date (MM/YY): Sep-12
    • Scope of Work:
      • Transportation, Installation Work and Pre-commissioning
      • 36″ Crude Export Pipeline
      • PLEM Installation (80 Ton)
      • Spool Installation
      • SPM with 6 x Anchored Chain
      • Underbouy hoses
      • 20″ Floating Hoses
      • 28″ Crude Export Pipeline
      • PLEM Installation(60 Ton)
      • Spool Installation
      • SPM with 6 x Anchored Chain
      • Underbouy Hoses
      • 20″ Floating Hoses
  • 40New Field Development ProjectPuteri Platform MalaysiaTL Offshore / New Field

    • Year: 2012
    • Vessel Name, Vessel Type, & Method(s): Kreuz Installer (DP DSV) Saturation Diving
    • Start Date (MM/YY): Aug-12
    • Completion Date (MM/YY): Aug-12
    • Scope of Work:
      • Transportation and Installation of Offshore Facilities
      • Installation of Grout Bags at EPCPP
  • 39Berantai Installation ProjectBerantai Field MalaysiaTL Offshore

    • Year: 2012
    • Vessel Name, Vessel Type, & Method(s): Kreuz Installer (DP DSV) Saturation Diving
    • Start Date (MM/YY): Jul-12
    • Completion Date (MM/YY): Aug-12
    • Scope of Work:
      • 12” Gas Export Riser Tie-in Work to PLET and close PLET valves
      • Mattresses installation for umbilical crossing
      • FPSO Mooring Chain Hook-up
      • 12” GEP Dynamic Riser Recovery and Hook-up
      • Umbilical Installation
      • 12” HP, 12” LP and 8” Dynamic Riser Hook up
      • Open PLET valves and PLET Mechanical Protection Installation
      • FPSO Floating hose installation
  • 38Cable Replacement ProjectChampion 7 Field BruneiBSP / SOC

    • Year: 2012
    • Vessel Name, Vessel Type, & Method(s): Resolute (Barge) Air Diving
    • Start Date (MM/YY): Jun-12
    • Completion Date (MM/YY): Jul-12
    • Scope of Work:
      • Installation of BUBUT Structural – Jacket & Topside
      • Installation of DANAU Structural – Jacket, Removal of Dummy Spool and Installation of T Piece Spool Topside
      • Installation of DANAU Flexible Pipeline
      • Installation of BUBUT Flexible Pipeline
      • CRP Project Cable Lay and J-tube Installation
      • Post Trenching of rigid pipeline to 775 m offshore from the shoreline
      • Hook-up Accommodation support to DAWJ-01 and BBWJ-1A
  • 37Transportation and Offshore Installation Services for BUMI-B…MalaysiaTLO / SOC

    • Year: 2012
    • Vessel Name, Vessel Type, & Method(s): Swiber PJW 3000 (Barge) Sat & Air Diving
    • Start Date (MM/YY): Jul-12
    • Completion Date (MM/YY): Sep-12
    • Scope of Work:
      • 24″ BMB to BMA Pipeline
      • BMB Jacket Installation
      • BMB Riser Installation
      • BMB Riser Clamp Installation (3 nos)
      • BMA Riser Installation
      • 10″ CKD to CKC Pipeline
      • CKC Riser Clamp Installation (4 nos)
      • CKC Riser Installation
      • CKD Jacket Installation
      • CKD Riser Installation
      • CKD Topside Installation
      • BMB Topside Installation
  • 36BAWAL and Tembang Development ProjectIndonesiaSwiber/ ConocoPhillips

    • Year: 2012
    • Vessel Name, Vessel Type, & Method(s): Kreuz Installer (DP DSV) Sat Diving & ROV
    • Start Date (MM/YY): May-12
    • Completion Date (MM/YY): Jul-12
    • Scope of Work:
      • Installation of 32.35 km Electro Hydraulic Umbilical from SDU-2(T-8 well) to SDU-1(Bawal-2 well)
      • Installation of 1.75 km Electro Hydraulic Umbilical from SDU-1(Bawal-2 well) to Bawal UTA(Bawal-1 well)
      • Installation of Flow Meter & Check Valve Protection Frame
      • Installation of EHFL Jumper between SDU-1 to Bawal well- 02
      • Installation of EHFL Jumper between UTA to Bawal well- 01
      • Trenching of the umbilical
      • Installation of Concrete Geo textile lined Mattress on the crossings along the Umbilical route
      • Tie-in between Bawal-02 well and 14” pipeline including installation of Venturi flow meters and check valves
      • Tie-in between 14” Bawal Pipeline and Keong Riser
      • Dewatering and Nitrogen packing of 14” Bawal Pipeline
  • 35B193 Development ProjectIndiaSOC/ONGC

    • Year: 2012
    • Vessel Name, Vessel Type, & Method(s): Swiber Concorde (Barge) Air Diving
    • Start Date (MM/YY): Apr-12
    • Completion Date (MM/YY): May-12
    • Scope of Work:
      • NB Riser Guard Installation
      • A. Air diving assistance on barge Victorious for MHNRD-II Project for riser guard installation – clean legs and installed Subsea support clamps at Platform WI-4
      • B. Air diving assistance on barge Conquest for MHNRD-II Project for riser guard installation – installed riser guard at WI-4: clean legs and installed subsea support clamps + riser guard at Platform LC
  • 34Transportation and Installation of Offshore Structures…BruneiBSP / Swiber

    • Year: 2012
    • Vessel Name, Vessel Type, & Method(s): Swiber Resolute (Barge) Air Diving
    • Start Date (MM/YY): Apr-12
    • Completion Date (MM/YY): Jun-12
    • Scope of Work:
      • Installation of BUBUT Structural – Jacket & Topside
      • Installation of DANAU Structural – Jacket, Removal of Dummy Spool and Installation of T Piece Spool Topside
      • Installation of DANAU Flexible Pipeline
      • Installation of BUBUT Flexible Pipeline
      • CRP Project Cable Lay and J-tube Installation
      • Post Trenching of rigid pipeline to 775 m offshore from the shoreline
      • Hook-up Accommodation support to DAWJ-01 and BBWJ-1A
  • 33Underwater Inspection Repair & Maintenance Services ProjectBruneiBSP / SOC

    • Year: 2012
    • Vessel Name, Vessel Type, & Method(s): Khawla 182 (Barge) Air Diving
    • Start Date (MM/YY): Mar-12
    • Completion Date (MM/YY): May-12
    • Scope of Work:
      • Sacrificial anodes replacements on 5 P/F
      • 5 X retrofit anodes installation
      • Grout sleeves installation
  • 32D1 – Pipeline Development ProjectD1 Field IndiaONGC / ESSAR

    • Year: 2012
    • Vessel Name, Vessel Type, & Method(s): Swiber PJW 3000 (Barge) Air Diving
    • Start Date (MM/YY): Feb-12
    • Completion Date (MM/YY): Jun-12
    • Scope of Work:
      Installation of pipelines
      • Cables
      • Flexible
      • Plem
  • 31D1 – Pipeline Development ProjectMumbaiSwiber / Essar / ONGC

    • Year: 2012
    • Vessel Name, Vessel Type, & Method(s): Kreuz Glorious (Barge) Saturation Diving & K-ROV 04
    • Start Date (MM/YY): Feb-12
    • Completion Date (MM/YY): May-12
    • Scope of Work:
      • Installation of pipelines
      • Cables
      • Flexible
      • Plem
  • 30B-46 ProjectMumbaiVML / ONGC

    • Year: 2011-2012
    • Vessel Name, Vessel Type, & Method(s): Seamec 3 (DP DSV) Sat & Air Diving
    • Start Date (MM/YY): Nov-11
    • Completion Date (MM/YY): Jun-12
    • Scope of Work:
      • Installation of Pipeline Crossing and Free Span Corrections
      • Installation of Tie-in Spools
      • Riser Clamps
      • J Tubes Clamps
      • J Tube
  • 29MHNRD II ProjectIndia, Mumbai HighValentine / ONGC

    • Year: 2011-2012
    • Vessel Name, Vessel Type, & Method(s): Swiber Victorious (Barge)
    • Start Date (MM/YY): Feb-12
    • Completion Date (MM/YY): Feb-12
    • Scope of Work:
      • Installation of Tie – in spools
  • 28B 46 Series ProjectIndia, Mumbai HighValentine / ONGC

    • Year: 2011-2012
    • Vessel Name, Vessel Type, & Method(s): Kreuz Supporter (Constructions Barge) Sat/ Air Diving
    • Start Date (MM/YY): Sep-11
    • Completion Date (MM/YY): Jun-12
    • Scope of Work:
      • Jacket face pre-engineering surveys Installation of Tie-in spools
      • Riser Clamps
      • J Tubes Clamp and J Tubes
  • 27MHN Pipelines ProjectIndia, Mumbai HighValentine / ONGC

    • Year: 2011-2012
    • Vessel Name, Vessel Type, & Method(s): Kreuz Supporter (Constructions Barge) Sat/ Air Diving
    • Start Date (MM/YY): Sep-11
    • Completion Date (MM/YY): Jun-12
    • Scope of Work:
      • Survey of Pipelines Crossing and Free Span Correction
      • Spool Tie-ins Installation of 12″ flanged riser
  • 26B 193 Field Development Subsea & Porcess Pipelines Project--

    • Year:
    • Vessel Name, Vessel Type, & Method(s): Installation of Riser and J-Tube Clamps Installation of 16″ stalk-on riser and 10″ J-Tube Jacket Face pre-engineering dive surveys
    • Start Date (MM/YY): Sep-11
    • Completion Date (MM/YY): Jun-12
    • Scope of Work:
      • Installation of Riser and J-Tube Clamps
      • Installation of 16″ stalk-on riser and 10″ J-Tube Jacket Face pre-engineering dive surveys
  • 25MHNRD II Project Swiber/ ONGCMumbaiSwiber/ ONGC

    • Year: 2011-2012
    • Vessel Name, Vessel Type, & Method(s): Swiber Conquest (Barge) Air Diving
    • Start Date (MM/YY): Feb-12
    • Completion Date (MM/YY): May-12
    • Scope of Work:
      • Installation of Tie – in spools
  • 24B-193 Process Platform ProjectMumbaiSwiber/ ONGC

    • Year: 2011-2012
    • Vessel Name, Vessel Type, & Method(s): PJW 3000 (Barge) Air Diving & K ROV 02 – Q11
    • Start Date (MM/YY): Dec-11
    • Completion Date (MM/YY): May-12
    • Scope of Work:
      • Installation of Process Platform + LQ + Flare Tripod
  • 23North Tapti Gas Field Development ProjectMumbaiSwiber/ ONGC

    • Year: 2011-2012
    • Vessel Name, Vessel Type, & Method(s): Swiber Magnificent (Barge) Air Diving
    • Start Date (MM/YY): Sep-11
    • Completion Date (MM/YY): Apr-12
    • Scope of Work:
      • SBM Installation
      • Grout Seal at NTP-2 Jacket
  • 22B193 5 Well Head ProjectMumbaiSwiber/ ONGC

    • Year: 2011-2012
    • Vessel Name, Vessel Type, & Method(s):
    • Start Date (MM/YY): Sep-11
    • Completion Date (MM/YY): Apr-12
    • Scope of Work:
      • Installation of B28 Jacket and Deck
  • 21 ICP-R Process Platform Project India, Mumbai HighAFCONS/ ONGC

    • Year: 2011
    • Vessel Name, Vessel Type, & Method(s): Kreuz Supporter (Barge), Swiber Atlantis (DP DSV), Swiber Concorde (Barge) – Sat/ Air Diving
    • Start Date (MM/YY): Mar-11
    • Completion Date (MM/YY): May-11
    • Scope of Work:
      • 24″ & 4.5 Subsea Pipe Laying
      • Tie-in Spool and Cable installation
  • 20 MHNRD-II Pipeline Project India, Mumbai HighSwiber/ ONGC

    • Year: 2011
    • Vessel Name, Vessel Type, & Method(s): Swiber Atlantis (DP DSV) Saturation Diving
    • Start Date (MM/YY): Jan-11
    • Completion Date (MM/YY): Mar-11
    • Scope of Work:
      • Installation of Pipeline Crossing
      • Free-span Correction
  • 19 North Tapti Gas Project India, North TaptiSwiber/ ONGC

    • Year: 2011
    • Vessel Name, Vessel Type, & Method(s): Kreuz Supporter (Constructions Barge) Sat/ Air Diving
    • Start Date (MM/YY): Feb-11
    • Completion Date (MM/YY): May-11
    • Scope of Work:
      • Installation of riser
      • Riser clamp
  • 18 MHN Pipeline Project India, West Coast/ Mumbai HighONGC/ Valentine

    • Year: 2011
    • Vessel Name, Vessel Type, & Method(s): Swiber Atlantis DP DSV (Saturation Diving)
    • Start Date (MM/YY): Feb-11
    • Completion Date (MM/YY): Apr-11
    • Scope of Work:
      • Installation of Pipeline Crossing
      • Free-span Corrections
  • 17 PL Platform and Pipeline Project India, West Coast/ Panna FieldBritish Gas/ ONGC/ RIL JV

    • Year: 2010-2011
    • Vessel Name, Vessel Type, & Method(s): Kreuz Supporter (Constructions Barge) Sat/ Air Diving
    • Start Date (MM/YY): Oct-10
    • Completion Date (MM/YY): Apr-11
    • Scope of Work:
      • Riser face pre-engineering survey at PPA Platform
      • Riser/ I-Tube Installation at PPA and PL Platform
      • Spool Tie-Ins at PPA and PL Platforms
      • Pre-Commissioning Support
  • 16 MHNRD-II Project India, West Coast/ Mumbai HighONGC/ MHNRD

    • Year: 2010-2011
    • Vessel Name, Vessel Type, & Method(s): Kreuz Supporter (Constructions Barge) Sat/ Air Diving
    • Start Date (MM/YY): Oct-10
    • Completion Date (MM/YY): Apr-11
    • Scope of Work:
      • Pre-engineering surveys installation of clamps
      • Risers & spool tie-ins
  • 15 Transportation Installation of Offshore Structures Pipelines Brunei/ OffshoreSBrunei Shell Petroleum (BSP)

    • Year: 2010
    • Vessel Name, Vessel Type, & Method(s): Constructions Work Barge (Sat/ Air Diving)
    • Start Date (MM/YY): Jul-10
    • Completion Date (MM/YY): Oct-10
    • Scope of Work:
      • Pre-engineering riser face survey
      • Installation of riser and spool tie-ins
      • Assist with flexible flow line installation and pipeline freespan corrections
  • 14Abondonment of Old Platform Project Brunei/ OffshoreSwiber/Brunei Shell Petroleum

    • Year: 2010
    • Vessel Name, Vessel Type, & Method(s): Swiber Chai Heavy Lift Barge (Air Diving)
    • Start Date (MM/YY): Jul-10
    • Completion Date (MM/YY): Oct-10
    • Scope of Work:
      • Cutting of Jacket legs and members for de-commissioning and removal of offshore platforms
  • 13CPOC Muda D Project Gulf/Thailand- Malaysia JDA Block B-17PTTEP/ CPOC/ Chevron

    • Year: 2010
    • Vessel Name, Vessel Type, & Method(s): Swiber Chai Derrick and Pipeline Lay Barge
      (Sat/ Air Diving)
    • Start Date (MM/YY): Mar-10
    • Completion Date (MM/YY): Nov-10
    • Scope of Work:
      • Pipeline spool tie-ins
      • Installation of risers and riser guard
      • Dive support during pipelay and precommissioning
  • 12Yadana Yangon Gas Oil Pipeline Project Myanmar/ Land Fall Point (Yangon)TOTAL/ MOGE

    • Year: 2010
    • Vessel Name, Vessel Type, & Method(s): Swiber Concorde Pipelay Barge (Air Diving)
    • Start Date (MM/YY): Feb-10
    • Completion Date (MM/YY): May-10
    • Scope of Work:
      • Diving support during pipeline beach pull activity
      • Connect davits and buoyance aids for surface pipeline tie-ins
  • 11Yadana Yangon Gas Oil Pipeline Project Myanmar/ YadanaTOTAL/ MOGE

    • Year: 2010
    • Vessel Name, Vessel Type, & Method(s): Swiber Aziz Constructions Work Barge (Sat/ Air Diving)
    • Start Date (MM/YY): Jan-10
    • Completion Date (MM/YY): Apr-10
    • Scope of Work:
      • Installation of riser
      • Pipelines
      • Spool tie-ins
      • Insertions of SMART plug in pipeline for spool tie-ins without flooding
  • 10Panna Gas Lift Project India, West Coast/ Panna FieldBritish Gas, ONGC, Reliance

    • Year: 2009-2010
    • Vessel Name, Vessel Type, & Method(s): Swiber (Kreuz) Supporter Constructions Work Barge (Sat/ Air Diving) (Air Diving)
    • Start Date (MM/YY): Oct-09
    • Completion Date (MM/YY): Jan-10
    • Scope of Work:
      • Riser face pre-engineering survey
      • Installation of riser and I/J Tubes
      • Spool Tie-ins
      • Repair to 1.25″ chemical lines in located in I-Tube
      • Installation of both landing and riser protectors
  • 9SFP Installation Project Indonesia/ Kakap Natuna FieldSwiber / Star Energy

    • Year: 2009
    • Vessel Name, Vessel Type, & Method(s): Swiber Glorious Constructions Work Barge
      (Air Diving)
    • Start Date (MM/YY): Oct-09
    • Completion Date (MM/YY): Jan-10
    • Scope of Work:
      • Removal of SBM/ FSCO and replacing with new SPM/ Reconnecting FPSO
  • 8BSP Farley Baram Project Brunei/ Farley BaramSwiber / Brunei Shell Petroleum

    • Year: 2009
    • Vessel Name, Vessel Type, & Method(s): Swiber Victorious Constructions Work Barge
      (Sat/ Air Diving)
    • Start Date (MM/YY): Oct-09
    • Completion Date (MM/YY): Nov-09
    • Scope of Work:
      • Repair of damaged pipeline and risers with subsea connectors
      • Spool tie-ins and riser installation
  • 7 Indonesia/ Kakap Natuna FieldSwiber / Timas / Star Energy

    • Year: 2009
    • Vessel Name, Vessel Type, & Method(s): Swiber Conquest Pipe Lay Barge (Air Diving)
    • Start Date (MM/YY): Oct-09
    • Completion Date (MM/YY): Nov-09
    • Scope of Work:
      • Air Dive support for pipe laying including stinger checks and pipeline profile monitoring
      • Installation
  • 6TLO – JMM Offshore MalaysiaTLO / PETRONAS

    • Year: 2009
    • Vessel Name, Vessel Type, & Method(s): Swiber Conquest Pipe Lay Barge (Air Diving)
    • Start Date (MM/YY): Aug-09
    • Completion Date (MM/YY): Sep-09
    • Scope of Work:
      • Air Dive support for pipe laying including stinger checks and pipeline profile monitoring
      • Stalk-on risers installation
  • 5TLO – JDA Block B17 Field Development Project Malaysia/ Thailand JDA Block B-17 FieldCPOC/ TLO

    • Year: 2009
    • Vessel Name, Vessel Type, & Method(s): Swiber Supporter Constructions Work Barge (Sat Dive)
    • Start Date (MM/YY): Jul-09
    • Completion Date (MM/YY): Aug-09
    • Scope of Work:
      • Installation of Pipeline Spool Tie-ins and Pre-commissioning Support
  • 4COPI North Belut Project Indonesia/ North BelutSwiber / Timas / Conoco Phillips

    • Year: 2009
    • Vessel Name, Vessel Type, & Method(s): Swiber Victorious Constructions Work Barge (Sat/ Air Diving)
    • Start Date (MM/YY): Mar-09
    • Completion Date (MM/YY): Aug-09
    • Scope of Work:
      • Installation of Pipeline Spool Tie-ins and Freespan correction
  • 3BG Hydra PK & SWP EPCI Projects India, West Coast/ Panna FieldBritish Gas, ONGC, Reliance JV

    • Year: 2009
    • Vessel Name, Vessel Type, & Method(s): Kreuz Supporter Constructions Barge, HD 2500(Sat/ Air Diving)
    • Start Date (MM/YY): Mar-09
    • Completion Date (MM/YY): May-09
    • Scope of Work:
      • Assist in recovery of four-legged jacket from seabed Pre-engineering riser face survey at PPA Platform
      • Installation of stalk-on risers and I/J tubes
      • Spools and pipeline crossings
    • Year: 2009
    • Vessel Name, Vessel Type, & Method(s): HD2500 Heavy Lift Derrick Barge (Air Diving)
    • Start Date (MM/YY): Feb-09
    • Completion Date (MM/YY): May-09
    • Scope of Work:
      • Dive support for jacket installation and pipeline activities
  • 2KG-D6 Field Development Project India, East Coast/ KG-6Reliance Industries Limited

    • Year: 2009
    • Vessel Name, Vessel Type, & Method(s): Rem Forza DP Vessel (Sat Diving)
    • Start Date (MM/YY): Oct-08
    • Completion Date (MM/YY): Jul-09
    • Scope of Work:
      • Installation of 24″ pipeline spool tie-ins Tie-in of 110T SSIVs
      • Pipeline, free spans correction using grout supports
      • Lateral and SSIVs stabilisation
      • Final pre-commissioning support
  • 1Hybrid Rentis Pipeline Installation ProjectMalaysia/ SarawakMurphy Oil

    • Year: 2008
    • Vessel Name, Vessel Type, & Method(s): Pipe Lay Barge(Air Diving)
    • Start Date (MM/YY): Aug-08
    • Completion Date (MM/YY): Sep-08
    • Scope of Work:
      • Air Diving support during Pipelay activities including stinger checks and pipeline profile monitoring
    • Year: 2008
    • Vessel Name, Vessel Type, & Method(s): Vessel Seabulk Takzim 4 Point Mooring DSV (Air Diving)
    • Start Date (MM/YY): Sep-08
    • Completion Date (MM/YY): Oct-08
    • Scope of Work:
      • Air Diving (-)40 MSW for pre-commissiong support from Vessel Seabulk Takzim
    • Year: 2008
    • Vessel Name, Vessel Type, & Method(s): Trenching Barge(Air Diving)
    • Start Date (MM/YY): Apr-08
    • Completion Date (MM/YY): May-08
    • Scope of Work:
      • Air Diving Support During trenching of 24″ Trunk Line
    • Year: 2008
    • Vessel Name, Vessel Type, & Method(s): DP Vessel(Air Diving)
    • Start Date (MM/YY): Apr-08
    • Completion Date (MM/YY): Jun-08
    • Scope of Work:
      • Pre-commissioning support.
      • Installation of Pipeline Crossing and free span support